-
feeding, mixing: Through the feeding system will be quantitative cement, foaming agent, stabilizing foam enhancer added mixer, dry mixed for 30 seconds;
-
stirring: The quantitative warm water into the mixer, wet stirring for 2 minutes; Add the quantitative foaming agent into the mixer for 8-15 seconds;
-
injection mold, foaming: The slurry is injected into the mold foam, foaming process of about 3-5 minutes;
-
the initial maintenance: injection mold After the completion of a number of hours for the initial maintenance;
-
demoulding: To be foamed cement insulation board to complete the initial coagulation, with initial strength can be demoulding;
-
cutting: With a certain intensity of foam cement insulation board blank after stripping can be cut, cutting specifications according to the need to adjust the cutting blades;
-
the finished product maintenance: Foam cement insulation Board maintenance period should be no less than 7 days
Page Url: https://www.cnsinowa.com/production-process-of-foaming-machine.html